Lechmere Viaduct Rehabilitation Project – MBTA Green Line $62M Light Rail Viaduct Rehabilitation

SPS was selected by the MBTA to complete the rehabilitation and replacement of track on the Lechmere Viaduct, an historic, 110 year old concrete arched structure. This project will provide a critical linkage to the stations being constructed as part of the Green Line Extension (GLX).

I-95 Piscataqua River Bridge Rehabilitation Project Wins Multiple Awards

Congratulations to the SPS Team and many dedicated subcontractors!

The award-winning I-95 Piscataqua River Bridge Rehabilitation project was a resounding success thanks to the efforts of the entire team including SPS New England, Inc. and T.Y. Lin International

From T.Y. Lin International:

“This project accomplished a major rehabilitation on perhaps the most important bridge in Maine and New Hampshire while maintaining traffic throughout. TYLin recognizes that a project of this magnitude would not have been completed on schedule, with no contractor claims, and with minimal impact on the traveling public if it were not for the dedication, teamwork, and “can do” attitude of all involved.

Special thanks go to Maine Department of Transportation, New Hampshire Department of Transportation, and the MTA for their coordination and cooperation with the project design team, and we are grateful for the excellent construction management team assembled by MaineDOT to oversee the project. TYLin appreciates SPS New England, Inc. prioritizing this project and working alongside the construction management and design teams to achieve success. The project was truly a cooperative effort, and the award recognition received is something for which the entire team can be proud.”

I-495 Haverhill Bridge Replacement Over Merrimack River Project Wins CMAA Award

We are pleased to announce the team of MassDOT – SPS – HNTB received an award from CMAA New England for the successful replacement of two long-span I-495 bridges over the Merrimack River in Haverhill, MA. The team was congratulated for its spirit of partnership that led to completing the project on-time in spite of the COVID pandemic.

SPS and Bond Civil & Utility Logan Airport Terminal C Joint Venture Project Recap (Video)

The Bond Civil & Utility – SPS New England Joint Venture is excited to share this video recapping a major milestone at Logan International Airport.

In the fall, the Terminal C Roadways project at Logan International Airport for The Massachusetts Port Authority successfully demolished two structures, installed the final bridge span, and re-opened a new roadway to Terminal C, working around the clock in only nine days.

Thank you to our Joint Venture partners Bond Civil Construction all craft employees and subcontractors involved who performed their work safely and on schedule; and our subcontractors, notably Select Demo, Atlantic Bridge and Engineering, Baycrane, Brox Industries, and Markings, Inc.

A special thanks to Windwood Productions LLC for working with the Joint Venture to produce this video.

I-95 and Dedham Street Canton, MA Project Complete

SPS is proud to announce the completion of another project for our valued client at MassDOT in Canton, along I-95 and Dedham St. This $50M project was years in the making and added a new off-ramp from I-95, replaced five bridges, upgraded public utilities, and improved a 1 Mile stretch of roadway.

This monumental task required crews to work seven days a week for months on end to meet the project completion date.

Congratulations and THANK YOU to all the dedicated SPS employees, subs and suppliers who worked together to deliver another Successful Project.

Special thanks to Phitted Media for producing this video.

SPS and RCC Green Line Surge Project

SPS forces deployed within the Boston Common to perform repairs to the tunnel roof above the MBTA Boylston Station. The work included on-track shoring of the existing tunnel ceiling in coordination with the overhead power and catenary.

As part of the Green Line Surge project SPS headed up the effort to perform concrete repairs within the MBTA Copley Station.

Crews performed crack injection and leak sealing work along an inaccessible stretch of the isolated MBTA D-Branch and then the busy, confined historical downtown tunnel corridor. SPS continues to respond quickly to the call for transit infrastructure repairs.

SPS and Railroad Construction Company (RCC) crews completed over 2,000 feet of rail and tie replacement. In the station platform pit areas, the team completed concrete and rubber insert installations.

I-495 Haverhill Bridge Replacement Over Merrimack River Project Wins ACEC-MA Gold Award

We are pleased to announce that the team of MassDOT – SPS New England – HNTB earned a Gold Recognition Award in the American Council of Engineering Companies (ACEC-MA) 2024 Engineering Excellence Awards (EEA) competition for the successful replacement of two long-span I-495 bridges over the Merrimack River in Haverhill, MA. The ACEC-MA Recognition Award is a prestigious distinction honoring projects demonstrating exceptional engineering excellence.

HCSS: SPS New England Wins Prestigious Award for $96M Haverhill Bridge Replacement Design-Build

Special thanks to HCSS for featuring our Award-Winning I-495 Haverhill Design Build Project.

From the article:

“SPS New England successfully navigated these challenges to deliver a much-needed infrastructure upgrade. Their expertise in bridge building has been a partnership with HCSS since 2002, when tighter profit margins required the company to shift from a revenue-based company that relied on accounting for relaying costs after-the-fact, to a company that could instantly measure daily costs using HeavyJob in 2005. Operating with a budget created directly from the estimate created in HeavyBid, SPS New England’s foremen can use their iPads in the field to track the time their crew spends on a specific phase of work against the budget set by the estimators.

With the seamless integration of HeavyBid to HeavyJob, the budgeted production rate from HeavyBid, along with logged man-hours, quantity tracking, and material tracking can inform the field if they are ahead or behind.

According to SPS – a resource and cost-loaded critical path method (CPM) schedule was used for this project. Implementing a CPM schedule in conjunction with the project controls of HeavyJob, HCSS provided the project management team with up-to-date job cost information, projected spending, and cost projections. This led to an overall best-practice management of the project’s budget. Change orders accounted for $4,043,729.81 (4.24 percent) of the project value; 90 percent of this amount was attributed to an owner-directed safety improvement for designing and constructing a slip ramp on the I-495 mainline.”

Discover the full story here

October 2024 MBTA Orange Line Railroad-SPS JV Trackwork

The Railroad-SPS New England JV recently completed a 13-day surge on the Orange Line as part of the MBTA’s ongoing Track Improvement Program, removing 6 speed restrictions between Jackson Square Station and the Mass Ave Tunnel Portal. Our work included various concrete repairs to 46 direct fixation track panels, core drilling and replacement of more than 130 track shoulder posts, over 11,000 feet of rail replacement including 64 thermite welds, replacement of 250 timber ties, and nearly 2000 feet of tamping. The JV also replaced various special track components at the Ruggles Crossovers, removing a longstanding movement restriction for Orange Line trains traveling through the switches. Our work was completed on-time with the help of SPS’s Bridge Deck & Joint Repair crews joining the track repair team.

Subcontractors: Fischbach & Moore, WL French, Tiabbi Equipment, CJ Shaughnessy Crane, Vanasse & Associates, Liro-Hill Group

 

September 2024 MBTA Redline Railroad-SPS JV Trackwork

Railroad-SPS New England worked 24 hours a day from September 6th to September 29th on a shutdown of the MBTA Red Line between JFK/UMass Station and Braintree Station with Railroad-SPS crews working between Tenean Beach and Wollaston Station. Railroad-SPS crews replaced over 7000 ties, just under 13000 feet of Rail, destressed over 34500 feet of rail, replaced the Linden Street Truck Pad, performed various switch work, as well has dressed the track with just under 3000 Tons of Ballast. The work performed by Railroad-SPS helped to lift (9) total speed restrictions and allow trains to travel at speeds up to 50 mph for the first time since the track was built.