Norton’s Point Bridge Rehabilitation
Manchester-by-the-Sea, MA
$1.6M
Norton's Point Association
Structures Maintenance
Project Overview
Project Overview
Originally constructed around 1912, the Norton’s Point Bridge spans a right of way controlled by the MBTA. The SPS Structures Maintenance Team worked closely with the owner and their engineer during this two-phase project to address cosmetic and structural concerns on a 375-foot section that spans the MBTA Commuter Rail.
Key Challenges:
Emphasis was placed on preserving the historic features of the bridge while increasing the longevity of the structure.
Repair Services Included:
- Vertical & Overhead Substructure Repairs
- Concrete Superstructure Repairs
- Erection of Ornamental Precast Railings
- Concrete Coating